Warehouse · Construction
Nusantara Logistics Hub
Location
Kawasan Industri Jababeka II
Client
PT Nusantara Logistik Terpadu
Year
2025
Contract value
Rp 128 M
Area
28.000 m²
Duration
16 bulan
Project overview
A 28,000 m² cross-dock distribution centre with 42 loading bays, 14 m clear height and a 2 MWp rooftop solar array.
The Nusantara Logistics Hub consolidates three regional warehouses into a single automated cross-dock facility. The steel portal-frame structure spans 60 m with pre-engineered trusses, a super-flat floor (FM2 tolerance) for VNA racking and a 2 MWp rooftop photovoltaic system.
The design-and-build contract includes civil works, structure, roofing, dock equipment coordination and a 3,200 m² office annex. AND Construction delivered the structural steel 3 weeks ahead of schedule through off-site fabrication and just-in-time erection sequencing.
Project timeline
From planning to handover
Phase 01 · Completed
Planning
Apr 2025 — Jul 2025
Design development, permits and budget.
Phase 02 · Completed
Tender
Jun 2025 — Aug 2025
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Aug 2025 — Sep 2025
Site setup, team and temporary works.
Phase 04 · In progress
Construction
Sep 2025 — Nov 2026
Structure, architecture and MEP.
Phase 05 · Upcoming
Handover
Oct 2026 — Nov 2026
Testing, commissioning and defect-free handover.
Phase 01 · Completed
Planning
Apr 2025 — Jul 2025
Design development, permits and budget.
Phase 02 · Completed
Tender
Jun 2025 — Aug 2025
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Aug 2025 — Sep 2025
Site setup, team and temporary works.
Phase 04 · In progress
Construction
Sep 2025 — Nov 2026
Structure, architecture and MEP.
Phase 05 · Upcoming
Handover
Oct 2026 — Nov 2026
Testing, commissioning and defect-free handover.