Infrastructure · Mobilization
Cisadane Link Bridge
Location
Sungai Cisadane, Karawaci
Client
Pemerintah Kota Tangerang — Dinas PUPR
Year
2026
Contract value
Rp 158 M
Area
8.400 m²
Duration
19 bulan
Project overview
A 420 m prestressed box-girder bridge with a 4-lane carriageway, dedicated cycle path and flood-resilient abutments.
The Cisadane Link connects two rapidly growing districts of Tangerang with a 420 m, 4-lane bridge over the Cisadane river. The superstructure uses balanced-cantilever prestressed box girders with a 120 m main span, founded on 1.5 m bored piles.
Awarded in August 2026 through public tender, the project is now in mobilization: site investigation, temporary works design and river-traffic management are underway ahead of piling works in November.
Project timeline
From planning to handover
Phase 01 · Completed
Planning
Jun 2026 — Sep 2026
Design development, permits and budget.
Phase 02 · Completed
Tender
Sep 2026 — Nov 2026
Estimate, BOQ and contract award.
Phase 03 · In progress
Mobilization
Nov 2026 — Dec 2026
Site setup, team and temporary works.
Phase 04 · Upcoming
Construction
Dec 2026 — Apr 2028
Structure, architecture and MEP.
Phase 05 · Upcoming
Handover
Apr 2028 — May 2028
Testing, commissioning and defect-free handover.
Phase 01 · Completed
Planning
Jun 2026 — Sep 2026
Design development, permits and budget.
Phase 02 · Completed
Tender
Sep 2026 — Nov 2026
Estimate, BOQ and contract award.
Phase 03 · In progress
Mobilization
Nov 2026 — Dec 2026
Site setup, team and temporary works.
Phase 04 · Upcoming
Construction
Dec 2026 — Apr 2028
Structure, architecture and MEP.
Phase 05 · Upcoming
Handover
Apr 2028 — May 2028
Testing, commissioning and defect-free handover.