Industrial · Completed
Mitra Farma Production Facility
Location
Kawasan Industri KIIC
Client
PT Mitra Farma Indonesia
Year
2021
Contract value
Rp 167 M
Area
24.800 m²
Duration
27 bulan
Project overview
A GMP-compliant pharmaceutical plant with ISO Class 7 and 8 cleanrooms, utilities building and a 6,000-pallet automated warehouse.
The facility houses solid-dose and liquid production lines under strict GMP requirements. AND Construction delivered civil and structural works, cleanroom envelope coordination, a dedicated utilities building (purified water, HVAC, compressed air) and an automated high-bay warehouse.
The project was executed with a zero-contamination site protocol and completed with successful IQ/OQ qualification support in May 2023.
Project timeline
From planning to handover
Phase 01 · Completed
Planning
Sep 2020 — Jan 2021
Design development, permits and budget.
Phase 02 · Completed
Tender
Dec 2020 — Mar 2021
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Apr 2021 — May 2021
Site setup, team and temporary works.
Phase 04 · Completed
Construction
May 2021 — May 2023
Structure, architecture and MEP.
Phase 05 · Completed
Handover
Apr 2023 — Jun 2023
Testing, commissioning and defect-free handover.
Phase 01 · Completed
Planning
Sep 2020 — Jan 2021
Design development, permits and budget.
Phase 02 · Completed
Tender
Dec 2020 — Mar 2021
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Apr 2021 — May 2021
Site setup, team and temporary works.
Phase 04 · Completed
Construction
May 2021 — May 2023
Structure, architecture and MEP.
Phase 05 · Completed
Handover
Apr 2023 — Jun 2023
Testing, commissioning and defect-free handover.
Project information
The details
More projects
Related work
Let's build what matters.
Tell us about your project — from early estimate to handover, one team and one source of truth.