Residential · Completed
Graha Sentosa Residence Phase 2
Location
BSD City, Serpong
Client
PT Graha Sentosa Propertindo
Year
2023
Contract value
Rp 142 M
Area
38.200 m²
Duration
30 bulan
Project overview
218 landed homes across 11 hectares with a clubhouse, linear park and complete estate infrastructure.
Phase 2 of Graha Sentosa Residence delivered 218 two-storey homes in four typologies, a 1,400 m² clubhouse and 2.3 km of estate roads with underground utilities. Precast wall panels and a standardized MEP kit-of-parts allowed a 14-day structural cycle per cluster.
Handed over in June 2025 with a defect rate below 0.4 items per unit.
Project timeline
From planning to handover
Phase 01 · Completed
Planning
Jun 2022 — Nov 2022
Design development, permits and budget.
Phase 02 · Completed
Tender
Oct 2022 — Jan 2023
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Feb 2023 — Apr 2023
Site setup, team and temporary works.
Phase 04 · Completed
Construction
Mar 2023 — Jun 2025
Structure, architecture and MEP.
Phase 05 · Completed
Handover
May 2025 — Jul 2025
Testing, commissioning and defect-free handover.
Phase 01 · Completed
Planning
Jun 2022 — Nov 2022
Design development, permits and budget.
Phase 02 · Completed
Tender
Oct 2022 — Jan 2023
Estimate, BOQ and contract award.
Phase 03 · Completed
Mobilization
Feb 2023 — Apr 2023
Site setup, team and temporary works.
Phase 04 · Completed
Construction
Mar 2023 — Jun 2025
Structure, architecture and MEP.
Phase 05 · Completed
Handover
May 2025 — Jul 2025
Testing, commissioning and defect-free handover.